Constructing The Cheops Pyramid Through Multispiral Ramps

Constructing the Cheops Pyramid Through Multispiral Ramps

The Cheops Pyramid is the largest Egyptian pyramid and is therefore also known as the Great Pyramid. It was built around 2600 BC and is considered the tomb of the Pharaoh Cheops with the Egyptian name Khufu. The pyramid is the oldest of the Seven Wonders of the Ancient World and the only one to remain largely intact.

Great Pyramid of Giza
[1]

The image from Mozaik Education shows the Pyramids of Giza from 4500 years ago. There is also a 3D representation of this.

The casing out of white limestone made the pyramids appear like diamonds in the sunlight.

Map of Egypt
[2]

 Contents

 
External Ramp
 Internal Ramp
 Theory of Multispiral Ramps

 Uniform Pyramid
 Ramp Construction
 Multispiral Model
 Towing Team
 Construction Time
 Workforce
 Turning At Corners
 Huge Blocks
 Zigzag Lifting
 Pyramidion
 Outer Casing
 Magnitude
 Real Pyramid
 Stability
 Measurements And Precision
 North-South Direction
 Strategy
 Numerology
 Seven Historical Evidences
 Summary
 Seven Misfortunes 
 Archaeological Finds 
 Interview with Gemini
 Publications


 View Complete Website

  • Although the Great Pyramid is one of the most impressive structures of mankind, there are almost no documents or archaeological finds that indicate its construction technique.
  • The pyramid builders belonged to a high guild, which probably kept their knowledge extremely to themselves. They made sure that all notes were destroyed.
  • According to the two historians Herodotus and Diodorus, the construction time was only 20 years.
  • How could the Egyptians in the Old Kingdom build this pyramid?
    There are many theories about this. However, most of which are completely absurd and none of them can explain the construction completely and satisfactorily. 
    Therefore, this problem is considered as a mystery of mankind.

External Ramp

Straight outside ramp of the Great Pyramid
[3]

Using an external ramp seems to be the most immediate method. This ramp model was proposed by Ludwig Borchardt in 1928.

With an inclination angle of 6.6 degrees or 11.6 %, the ramp would have a length of 1.3 km and a volume of 160 % relative to the pyramid.

Since the two neighboring pyramids did not exist at that time, the ramp could have looked like demonstarted in the image. This is probably the only way to place an external ramp in this landscape.

  • It would take more than 10 years to remove this ramp. Therefore, it is impossible to complete this monument within 20 years
  • If this critical time limit would not exist, then the external ramp would have been considered as a possible solution to the problem for long.

Internal Ramp

In 2003, Jean-Pierre Houdin introduced his theory of the internal ramp, which uses two separate ramp systems.

A straight external ramp leads to 30 % of the height, what allows to install 65 % of the material.

The remaining material is installed using an internal ramp, which requires a second technique.

This theory has generated great fascination worldwide through computer simulations. However, the crucial aspect, namely functionality, is never questioned.

1) The internal ramp, which is 2.6 m wide, has only a single transport lane. Therefore, the construction of 35 % of the material would take at least 25 years. Thus, the total construction time of the pyramid would be at least 35 years. To achieve the unavoidable construction time of 20 years, there would have to be an average of more than 2.5 transportation lanes in the upper 70 % of the pyramid. See the Construction Time section.

2) In the upper 15 % of the pyramid, the inner ramp technique leads to a dead end. Space within the pyramid becomes increasingly limited, and the tunnel project cannot continue. Therefore, the construction of the uppermost part of the pyramid and the setting up of the pyramidion must be accomplished using a third technique. 

3) For the way back, a wooden frame (green) is installed, which represents a fourth technique. The wooden frame rests on the stones of the outer casing and is only supported by the bosses of these stones, what is a high risk of accidents

4) For the smoothing process of the outer layer, an additional wooden frame must be attached around the pyramid, which must be moved from top to bottom according to the smoothing process. See the Outer Casing section.

Overall, a construction method using at least four different techniques contradicts the customs of the Old Kingdom, according to which the construction method was simple and uniform.

Therefore, other solutions must be found.

Theory of Multispiral Ramps

This section contains the essential informations on the Theory of Multispiral Ramps. Detailed information, including calculation tables, is provided below.

  1. The construction of the pyramid was the largest and most important project in the state.
  2. This required a clear and controllable technology, otherwise the project would never have been started.
  3. The pharaoh had to be alive when the pyramid was completed.
    Therefore, the construction period was set at 20 years.
  4. The slope of the pyramid was determined for symbolic or political-religious reasons:
    Slope = 4/π  
  5. Then the task was to build the largest possible pyramid in this format.
    There were two limitations:
    – Construction time of 20 years,
    – Average number of workers of 12,000 under normal working conditions.
  6. This determined the height of the pyramid to be 146.59 m.
  7. Overall, this is an early optimization problem:
    To create the largest possible pyramid under certain constraints.
    This task could only be solved by the earliest mathematicians.
  8. A precise construction plan and schedule had to be submitted, specifying which height would be reached at what time.
    For example, „After one-third of the time, 50 % of the material has been used, but only 20 % of the height has been reached.“
    See the Overview Image.
  9. Therefore, the most efficient method had to be applied at every stage of the construction process.
    Deciphering the construction process is therefore quite analogous to convergent evolution in biology.
  10. Using several spiral ramps is the most efficient construction method:
    – The system has sufficient delivery lanes,
    – There is a separate return path to avoid collisions,
    – The delivery of stone blocks and the construction of the ramps can be carried out independently of each other,
    – The ramp material accounts for only 6 % in comparision to the pyramid’s volume.
    See the Multispiral Model section.
  11. The transport method using wooden rollers is the most efficient.
    The method using sliding sleds on wooden beams also requires numerous water carriers and wider ramps.
    See the Towing Team section.
  12. The bottleneck of the system is not the number of delivery lanes, but the number of workers.
    See the Construction Time section.
  13. The multispiral ramp theory is the first coherent and complete proposal for the construction of the Great Pyramid.
    This was published in 2024.
  14. The construction method is consistent with the few archaeological finds and historical evidences.
  15. The task of future archaeologists will be to examine the outermost layer of the pyramid for ramp traces.

Uniform Pyramid

To better understand the construction of a pyramid, let’s consider a uniform step pyramid with 5 levels. All stones or blocks have the same shape.

The number of blocks is calculated from top to bottom as follows:
B = 1 + 22 + 33 + 44 + 55
   = 1 + 4 + 9 + 16 + 25
   = 55

Then the inner step pyramid is decorated with an outer casing. The corner and deco stones of the casing are placed on the steps of the inner pyramid.

There is an additional level with a gold-plated keystone at the very top. This stone is a mini pyramid and is called pyramidion.

The Great Pyramid consists of 210 levels including the Pyramidion. As a uniform pyramid, the Great Pyramid would have 3 million blocks.

The lowest red line indicates the height at which half or 50 % of the material was installed. This process took 6,4 years and only a height of 20.5 % was reached at that point.

The blue line shows the height after half of the construction period or after 10 years, where one third of the height has been reached and 70% of the material has been used.

The green line stands for half of the height or the median. This construction phase was reached after almost three-quarters of the construction period or 14.2 years.

Thus, for many years the Pharaoh saw only a truncated pyramid which did slowly grow.

Multispiral Model

The main green path begins on the south side, about 400 m from the quarries, from where 99 % of the material is delivered. See the image of the Giza Plateau.

The main ramp leads to the top of the pyramid. In the upper third of the pyramid, the ramp paths partially rest on the path below. This creates a working platform at the top of the pyramid, allowing the pyramidion to be placed on top.

When transporting a block from the bottom to the top, a distance of 1.8 km is covered and 7.5 circuits are made. The transport takes 8.8 hours. The values are given in detail per level in Table 3.

On the other 3 sides there start 2 ramps with only one transport lane.

These 6 single paths end at different heights. The ends are marked in red.

The entire model consists of 7 spiral paths.

The dark blue ramp ends at the north entrance which is marked in black. This was a restricted access area.

  • The green main ramp has 6 lanes in the initial phase. The outer 3 lanes are marked by orange lines. After the first turn of the ramp after 5 years, the outer 3 lanes can be dismantled and the ramp material can be reused further up. Compare the images Construction Time and Huge Blocks
  • The dynamic ramp construction is carried out in 3 steps, whereby 40 % of the ramp material is recycled or saved.
  • The total ramp material has a volume of only 6 % of the volume of the pyramid. This is a huge advantage over the external ramp, which has a volume of 160 %. The values are given in detail per level in Table 3.
  • The many ramp paths make it possible to create a working platform at any location for the later application of the outer casing.

Towing Team

A towing team of 20 workers is required to transport a 2.3 ton block.

At the command of the commander (4), 12 workers (5) pull simultaneously for 1.3 seconds with a force of 23 kp. This moves the sledge with the block by 25 cm. During the pulling movement, the workers make the same sound.

The two workers (6) on the right are enjoying the break.

The two workers (3) with the wooden bares ensure that the rollers remain parallel and do not jam.

After the pulling movement, the sledge stands for 2.7 seconds while the towing workers (5) reposition themselves.

The two workers (3) clamp the wooden bars between the rollers, what prevents the sledge from rolling back.

The worker (1) on the far left must always stand behind the sledge and catch the rollers. This prevents the rolls from falling off the pyramid, which is a massive risk of accidents.

The two workers (2) transport the rollers from back to front and reposition them.

  • Each transport lane has a width of 3 block lengths or 3.3 m.
  • After a ramp length of 5.5 block lengths or 6 m, the height of one level or 0.7 m is reached.
  • Within 4 seconds the team moves 25 cm, which corresponds to a speed of 3.75 m/min.
  • The teams have a freedom of movement of 18.75 m. This is marked with the blue lines.
  • One block can be delivered per lane every 5 minutes.
  • Thus, 0.2 blocks are delivered per minute.
  • This corresponds to 12 blocks per hour.
  • For a working day of 12 hours per day in two shifts, this corresponds to 144 blocks per day and per lane.
  • All teams must move at the same speed to avoid jams.
  • The workload of the workers over 6 hours with rotating breaks and relaxation on the way back can be compared to today’s working conditions and in no way corresponds to slave conditions.
  • To ensure smooth transport with rollers, the surface of the ramps should be kept flat and stable.

In the literature, there are almost exclusively presented a transport method in which sledges were pulled over wooden beams. The beams were constantly lubricated with Nile mud to reduce friction. See the picture by Peter Jackson.

A towing team would consist of 25 workers and would be 5 workers larger than when transporting with wooden rollers due to the higher friction.

However, water carriers were required in addition when using Nile mud.

  • The water carriers would have to deliver the Nile mud not only at the end of the delivery lane, but for all towing teams along the entire transport lane.
  • When building the upper half of the pyramid, the routes are longer than 1 km and up to 80 teams would be on one transport lane. Therefore, the number of water carriers would increase considerably.
  • The water carriers would require a separate walkway as they are large in number and would move at 8 times the speed of the towing teams. This way is marked by the two blue lines. Therefore, the ramps would need to be 20 % wider. This would increase the ramp volume by 44 %. The same applies to the number of workers for ramp construction.
  • For example, let’s look at level 112, where 90 % of the volume was built up. At this point, an additional 1,747 water carriers would be required, which are missing for other tasks, as shown in Table 4. In this case, the number of blocks installed per day would be 279, whereas the corresponding number for the transport method using wooden rollers is 380.
  • In addition, the workers would have difficulty moving on the slippery transport paths.
  • Under the same working conditions, it can be said that with this transport technique, the construction time would increase by 6 years and the total work by 33 %. The detailed values and comparison are shown in the appendix of Table 4.
  • The greatest possible efficiency was required at every stage of the process, because the project was a fight against time.

Construction Time

The image shows level 112, where 90 % of the material has been installed.

The pyramidion was transported up to there from level to level by zigzag-lifting. All the huge blocks had been installed by then. Compare the image Huge Blocks.

The main green path leads to this level with 3 lanes. In the lower area, the ramp material of the 3 outer lanes was transported upwards (dynamic reuse).

There are also the light blue and dark purple paths, each with one lane. So a total of 5
 lanes lead to this level. When subtracting one lane for the way back, there are still 4 lanes left for delivering the blocks.

  • This level has a width of  210  112 = 98  block widths.
  • Therefore, level 112 consists of  98  98 = 9,604  blocks.
  • There can be 144 blocks delivered per day and per transport lane. 
  • At this stage, at full capacity, there are 45 towing teams on one lane. This requires 4,583 workers per day over 2 shifts. The exact method of calculating the number of workers is shown in Table 1.
  • During the three-month Nile flood, the maximum number of 20,000 workers are available. Therefore, 20,000 / 4,583 = 4.36 lanes could be operated. In the upper 70 % of the pyramid, the maximum number of workers can no longer be utilized, as space becomes increasingly limited toward the top. Only 5 lanes, and thus 4 delivery lanes, are available. This means  4  144 = 576 can be delivered per day.
  • In the remaining 9 months outside of the Nile flood, there were only 10,000 workers. Therefore, 10,000 / 4,583 = 2.18 lanes could be operated during this time. This would allow 2.18  144 = 314 blocks to be delivered per day.
  • This results in an annual average of 380 blocks per working day, using 2.64 transport lanes.
  • Therefore, this level has a construction time of  9,604 / 380 = 25.3 working days.
  • Since there were 300 working days per year, this corresponds to 25,3 / 300 = 0.084 years or approximately one month.
  • In this way, the values for all 210 levels can be determined. Adding the values up to level 112 results in a construction time of 14.8 years at this point. See the Overview Image.
  • By adding the values for all 210 levels results in the construction time of 18.4 years for the inner step pyramid. Detailed values are shown in Table 2.
  • This leaves 1.6 years of the total construction time of 20 years. This is enough time to install the outer casing, remove the ramps, and construct the perimeter wall.
  • The outer casing requires only 0.7 % of the material, but must be polished smooth.
  • Table 1 gives a condensed overview of how the number of transport lanes decreases with increasing height of the pyramid, but the number of workers for towing increases.
  • Table 2 shows how, with increasing height, the individual levels have fewer blocks. Overall, the construction times for the different levels decrease slightly with increasing height.
  • Table 3 contains some key figures, e.g. the „number of blocks per minute“ which has a value of 1.4 at the lowest level and 0.2 at the highest level.
  • This model proves that the system of spiral ramps has sufficient transport capacity in the upper range of the pyramid. This is in contradiction to the literature. There are only models used that have only one transport lane in the upper two thirds of the pyramid without a separate way back. In this case the construction period would be at least 30 years.
  • The transport problem can be completely solved with the described system of ramps. No further technology is necessary. This is contrary to the literature where it is mentioned that ramps require supplementary devices.

The diagram shows how the volume and height of the pyramid developed within the construction period of 20 years.

The blue dashed line indicates that after 10 years one third of the height was reached and the volume of 70 % was builtSee the corresponding image in the Uniform Pyramid section.

The black dashed line indicates that the height of 100 % was reached after 18.4 years when the pyramidion was placed.

Then the outer casing was installed from top to bottom in 1.6 years, so that the construction was completed after 20 years

Zigzag Lifting

Spiral ramps are repeatedly criticized for not being able to transport the 70-ton blocks to the required height. Therefore, they are not considered a serious solution to the problem.

The multispiral ramp model uses a wide ramp (green) with a width of 9.9 m, which allows for the transport of large blocks. There is also a more elegant and efficient method. 

During the first 5 years, the huge blocks were brought to the surface of the pyramid using the green ramp..

The huge blocks could then be transported upwards from level to level using temporary ramps (red) with a slight gradient of 2 degrees. 

With this transport method, the huge blocks only had to be moved back and forth. There was no need to turn them at any corners.

The area on the pyramid was always so large that all the huge blocks never required more than 15 % of the area.

The image illustrates the method of the Zigzag Lifting.

On the left, there is a huge 70-ton block (black). It’s supported on wooden planks (purple) and was moved to this position using the temporary green ramp.acht.

The green ramp was then removed and the dark blocks were installed. Then the temporary red ramp was built and the huge block was transported to the right side, lifting it one level.

Outer Casing

When the pyramidion was placed, the bottom-up process is completed.

Then the outer casing was installed in a top-down process. At the same time the ramps were removed.

The white limestone was delivered from Tura, 30 km away.

Summary

 
  • The method used is the efficient application of two techniques known at the time: 
    spiral ramps out of mud-bricks and transport with wooden rollers.
  • The construction followed a uniform and simple procedure, which was common in the Old Kingdom. This was a necessary prerequisite for systematically employing thousands of workers over the years.
  • Overall, it is about the optimization of a dynamic ramp system.
  • The method solves the problem one hundred percent technically and logistically, so there are no unanswered questions in this regard.
  • Furthermore, the method is consistent with the previous „Seven Historical Evidences“. So far, there are no contradictions due to historical or archaeological findings.
  • The Multispiral Model proposed by Rudolf Volz in 2024 is the first functional theory for the construction of the Great Pyramid. It is considered a further development and completion of the work of  Dows Dunham and Walter Vose from 1956.
The following image shows the evolutionary lines of the ramp models.
 

Interview with Gemini

In July 2025, Rudolf Höld had an interview with the AI Gemini regarding the topic of „Discrediting the Spiral Ramps“. These are the final statements:

Rudolf Volz’s Multispiral model is impressive for its plausibility, consistency, and elegance. It explains how the monumental Great Pyramid could have been built using the familiar resources and practices of the Old Kingdom, addressing the major challenges with engineeringly comprehensible and logistically intelligent solutions based on simple principles and outstanding organization.
This makes it one of the best-explained theories currently available for the construction of the Great Pyramid of Giza.

The phrase „Logistical masterpiece instead of technical marvels“ perfectly summarizes what makes the Multispiral model so compelling and why previous approaches may have reached their limits.

Here is the full interview. 

Publications

In January 2024, the Mitteldeutsche Zeitung published a newspaper article entitled Mystery of History Solved  on this theory.

There will be an additional scientific paper that will cover this website in detail and include the mathematical proofsIt will give an insight into the mathematical thinking at the time 5000 years ago, explaining exactly how they were able to use these methods to create this monument with such precisionThe work includes positioning the roof over the north entrance with blocks of 100 tons and erecting obelisks of 400 tons.
The work is titled Modeling The Great Pyramid and will be published in the Journal of Humanistic Mathematics of the Claremont Colleges in California at the end of 2025.

The three-dimensional CAD models were created by Rudolf Höld using the moi3d software. He also conducted the interviews with the various AIs.

The idea, proof finding and implementation were developed by Dr. Rudolf Volz. He is a qualified mathematician, has developed software for many years and is interested in the central problems of humanity. 

 Sources: Image 1 and the background of Image 3 are courtesy of Mosaik Education.
Image 2 uses elements from 123rf.com.
Image 4 is by Gouchet and image 6 is by Dows Dunham.
Image 5 is by Peter Jackson, Bridgeman Images.
All other images are copyright of Dr. Rudolf Volz.